Storage for Return Waste from Metallurgical Production for Umicore Med AD, Pirdop

Project EE 080/0701/CW

Designer and contractor: Geotechmin OOD

Project execution period: 2001 – 2002

Description of the project:

The project includes the design and construction on a new covered storage for return waste for Umicore Med AD. The total area of the storage is 3 200 sq.m. The walls are 4 m high with built in steel plates for protection against demolition by loading machines. A steel structure which weights 205 tons is installed on top of them. The roof structure and the walls are covered with LT-sheet iron and PVD-screen for protection from the aggressive environment.

Conducted works:

  • Concrete – 2,354 cub.m.
  • Formwork – 3,700 sq.m.
  • Reinforcement – 190 tons
  • HDPE smooth liner, 2 mm thick – 14,050 sq.m.
  • Steel structure – 205 tons
  • Implemented steel plates, 20 mm thick – 27 tons
  • Demolition of reinforced structures and elements – 14,050 cub.m.
  • Breaking of reinforced concrete pieces with a crusher and separation of the construction steel – 14,050 cub.m.
  • Breaking of concrete structures and elements – 21,630 cub.m.
  • Landfilling of contaminated concrete – 21,630 cub.m.
  • Making of an asphalt road within the plant – 1.3 km
  • Making of an asphalt platform – 2,100 sq.m.
  • Collection, loading and transportation of contaminated soil to a landfill – 4,100 sq.m.
Excavation works
Preparation of the foundation
Concrete works
Waterproofing works