Reconstruction of Tailings Pond “Buhovo” – Stage II

PHARE Project BG9807-03-01

Employer: Ministry of Environment and Water, Bulgaria

Project execution period: 2000 – 2001

Geotechmin OOD implemented this project jointly with OEC Bulgaria EOOD.

Conducted works:

  • Clay fill – 600,000 cub.m.
  • Drainage layer – 130,000 cub.m. of gravel
  • New drainage system – concrete pipes, diameter 300 mm – 2,100 m
  • Underground concrete reservoir – 500 cub.m.
  • Pumping station equipped with two pumps, controls and automatics
  • Pipeline – 300 m
  • Transformer station
  • Repair of dewatering ditch
  • Construction of concrete barrage
  • Landslide strengthening works
  • Piezometers
  • Temporary roads – 13 km
Preparation works
Forming of the slope
Reinforced concrete culvert